Current Project Status

  • Phase One of alkalinity additions were completed in the Fall of 2024
  • Phase Two of alkalinity additions are scheduled to begin in late Spring of 2025
Project Overview

Project Timeline

September 2023
October 2023
October 2024
Spring 2025
September 2023

Project awarded funding by the NOAA Ocean Acidification Program (OAP) on behalf of the National Oceanographic Partnership Program (NOPP). 16 other projects dedicated to marine carbon dioxide removal were also funded.

October 2023

Early-stage project development begins on site.

October 2024

Initial small-scale dosing scheduled to began on October 28th, 2024. Additions will continued for one week. 

Spring 2025

Second-stage dosing scheduled to begin in late spring, with additions continuing for approximately four weeks.